What types of building inspections are required for work done under a permit?
In most cases, both rough and final inspections are required for all inspection trades - structural, electrical, plumbing and mechanical. Call 311 or 847-448-4311 or submit a "Building Inspection Request" online here: https://www.cityofevanston.org/how-to-/311/submit-a-request
A person representing the permit holder has to be on site at the time of the inspection. Sub-contractors need to be onsite at the time of the inspection.
Once the inspection is completed, a field inspection report will be emailed to the contractor. Copies of field inspection reports are required with the application for a Certificate of Occupancy once the project is completed.